Mine / resource · Australia
Expansion FID approved 30 Sep 2026, targeting ~780 kt/yr SC5.4 from FY30 with first incremental tonnes in FY28.
| Listed owner | Stake | kt SC/yr | kt LCE/yr |
|---|---|---|---|
| Liontown | 100% | ≈417 | ≈52 |
Structure: Liontown Resources.
| Jun Q 26 | Mar Q 26 | Dec Q 25 | Sep Q 25 | Jun Q 25 | Mar Q 25 | |
|---|---|---|---|---|---|---|
| Production (kt SC) | 103.1 | 96.4 | 105.3 | 87.2 | 85.9 | 95.7 |
| Sales (kt SC) | 108.5 | 83.9 | 112.1 | 77.5 | 97.3 | 93.9 |
| Implied inventory change (prod − sales) | −5.4 | +12.5 | −6.8 | +9.7 | −11.4 | +1.8 |
| Unit cost (AUD/t) | 995 | 981 | 910 | 1,093 | 898 | 816 |
| Realised price (US$/t) | $1,880 | $1,845 | $985 | $691 | $740 | $815 |
| Implied cash margin (US$/t) | +$1,233 | +$1,207 | +$394 | −$19 | +$156 | +$285 |
$10,203/t LCE · cheaper than about 3% of costed supply
Stable fiscal regime; royalty set by the state. source
| Date | Field | Change | Source |
|---|---|---|---|
| 24 Oct 2026 | Realised price | Spodumene US$740/dmt · Jun Q 2025 · SC6 equiv. | Liontown June 2025 Quarterly Activities Report (29 July 2025) |
| 24 Oct 2026 | Milestone | Apr 2025 · Underground production stoping commenced at Mt Mann First production Completed | Liontown June 2025 Quarterly Activities Report (29 July 2025) |
| 24 Oct 2026 | Realised price | Spodumene US$815/dmt · Mar Q 2025 · SC6 equiv. | Liontown March 2025 Quarterly Activities Report (24 April 2025) |
| 24 Oct 2026 | Quarterly figures | Jun Q 2025 · production 85.892 kt SC · sales 97.33 kt SC · cost AUD 898 (FOB per dmt sold) | Liontown June 2025 Quarterly Activities Report (29 July 2025) |
| 24 Oct 2026 | Quarterly figures | Mar Q 2025 · production 95.709 kt SC · sales 93.94 kt SC · cost AUD 816 (FOB per dmt SC6e sold) | Liontown March 2025 Quarterly Activities Report (24 April 2025) |
| 24 Oct 2026 | Milestone | 1 Jan 2025 · Commercial production declared at Kathleen Valley process plant (effective 1 Jan 2025) Other Completed | Liontown March 2025 Quarterly Activities Report (24 April 2025) |
| 24 Oct 2026 | Milestone | Q4 2028 · Expansion construction completion (end of Q2 FY29) Expansion Expected | Liontown: Kathleen Valley Expansion Final Investment Decision (30 September 2026) |
| 24 Oct 2026 | Milestone | 29 Oct 2026 · September 2026 quarterly activities report Report Expected | Liontown: September 2026 Quarterly Webcast – Update (22 October 2026) |