80 kt lithium salts: 50 kt LiOH + 30 kt Li2CO3 (IR record 27 Mar 2025); Phase 3 adds a 30 kt LiOH line (in commissioning per IR record 12 Nov 2025). Group total 'nearly 130 kt' across Ya'an and Guoli ≈ 74 kt LCE/yr (nameplate)
Location
29.98°, 103.12°
Address 四川省雅安市经济开发区永兴大道南段99号 (Mingshan district, Ya'an). Lat/lon = China MEE pollutant discharge permit production-site coordinates for 雅化锂业(雅安)有限公司, permit 91511800MA64KJ5D0G001V
Ownership structure
Effective economic interest of listed owners · As of 25 Oct 2026
Conversion refineryYa'an Lithium (Yahua)80 kt lithium salts: 50 kt LiOH + 30 kt Li2CO3 (IR record 27 Mar 2025); Phase 3 adds a 30 kt LiOH line (in commissioning per IR record 12 Nov 2025). Group total 'nearly 130 kt' across Ya'an and Guoli
Country risk · China
Policy risk: MediumAs of 24 Oct 2026
Change history
Approved changes with their source · As of 25 Oct 2026