Mine / resource · Chile

Salar de Atacama (Albemarle)

ProducingVerified 24 Oct 2026As of 24 Oct 2026
Owner
Albemarle
Listed via
ALB
Product
Brine
Deposit type
Brine
Capacity
2025 production 14 kt Li metal (≈75 kt LCE at 0.1878 t Li per t LCE), 100% attributable; brine concentrate trucked to La Negra
≈ 85 kt LCE/yr (nameplate)
Location
-23.62°, -68.35°
Source
Filing used for verification

Reserves fell 33% to 308 kt Li metal at 31 Dec 2025 after pumping was reduced under Albemarle's early warning plan; DLE with reinjection is being studied.

Ownership structure

Effective economic interest of listed owners · As of 24 Oct 2026
AlbemarleALB100%Salar de Atacama (AlbeMine / resource

Attributable capacity

Listed ownerStakekt LCE/yr
Albemarle ALB100%≈85

Structure: Albemarle.

Value chain

Owners, buyers and the refineries on Li3atlas they feed · As of 24 Oct 2026
Mine / resourceSalar de Atacama (Albemarle)2025 production 14 kt Li metal (≈75 kt LCE at 0.1878 t Li per t LCE), 100% attributable; brine concentrate trucked to La Negra

Resource and mine life

As of 24 Oct 2026
Mine life
15.75 years

Milestones

As of 24 Oct 2026

Completed (1)

  • Mar 2026DLE environmental assessment submitted (permit application, 1 DLE train, up to 6 sought)Permit · source

Country risk · Chile

Policy risk: Medium As of 24 Oct 2026

State-led model: Codelco holds 50% plus one share of NovaAndino Litio, which runs SQM's Salar de Atacama operations until 2060 (deal closed Dec 2025). source

Change history

Approved changes with their source · As of 24 Oct 2026
DateFieldChangeSource
24 Oct 2026Milestonenew: Mar 2026 · DLE environmental assessment submitted (permit application, 1 DLE train, up to 6 sought) Permit CompletedAlbemarle Q2 2026 earnings presentation (6 Aug 2026), Energy Storage Quarterly Sales Metrics
24 Oct 2026Mine lifenew: 15.75Albemarle Form 10-K for fiscal year 2025 (filed 11 Feb 2026)
24 Oct 2026CapacityBrine feed for La Negra → 2025 production 14 kt Li metal (≈75 kt LCE at 0.1878 t Li per t LCE), 100% attributable; brine concentrate trucked to La NegraAlbemarle Form 10-K for fiscal year 2025 (filed 11 Feb 2026)
24 Oct 2026NotesCORFO lease runs to 2043. → Reserves fell 33% to 308 kt Li metal at 31 Dec 2025 after pumping was reduced under Albemarle's early warning plan; DLE with reinjection is being studied.Albemarle Form 10-K for fiscal year 2025 (filed 11 Feb 2026)
24 Oct 2026VerifiedValues confirmedAlbemarle Form 10-K for fiscal year 2025 (filed 11 Feb 2026)